11.22.1 |
Environmental Issues
Water management: The nature of the underground mining has resulted in the propagation of extensive
cracks to surface. These cracks create a preferential flow path for water into the mine, resulting in
significant decant from the adits. Hlobane is in the process of sealing the cracks along the stream on the
top of the mountain. The mine has predicted that this will reduce ingress into the mountain and by
implication decant, by about 50%. It is not expected that any significant acidity will be produced
underground, however, the decant is saline with sulfate, calcium and sodium being the major contributors.
Currently, decant is not treated and discharges straight to a watercourse. Evaporation control dams have
been constructed on the northern side of the mountain, however, these have insufficient capacity to handle
water made, resulting in a discharge to a watercourse. The open pits have been backfilled and the surface
rehabilitated, however, uncontrolled decant is evident at the pits, particularly those lower down the slopes.
Existing water uses have been registered and an application for a water use licence was submitted to
DWAF in 2002. To date there has been no indication from the authorities as to when the licence will be
issued.
Waste disposal: Three of the four discard dumps have been rehabilitated by capping with a clay layer,
followed by top-soiling and vegetating. This rehabilitation has reduced seepage, however, saline water still
emanates from the dumps. Although this is not treated, Hlobane has made a provision for water treatment.
The provision made is for the construction of passive treatment reactors at each location requiring
treatment. The fourth dump (Gus dump) is still operational and is being utilised by the contract miner for
waste disposal. This is being operated as a co-disposal facility, with coarse discard used to contain the
fines. During deposition, some compaction of the coarse fraction is undertaken to limit oxygen and water
ingress. At closure this dump will require clay capping, top-soiling and vegetating. It is expected that this
dump will decant, also requiring treatment. SRK is of the opinion that an adequate provision has been
made for the closure of the dump.
Water treatment: The mine expects to implement passive water treatment, to remove the sulfates and iron
from decant water. This technology is still in the development phase (bench and small pilot scale) and has
not yet been tested on a large industrial site. Therefore, there is a potential risk that treatment may not
successfully be converted to the large pilot and industrial scale. Should passive water treatment not prove
successful at the industrial scale, there is a risk that Hlobane could be required to implement already
proven technology for water treatment. It is estimated that if this is required, the costs would be in the order
of ZAR150 – 200m for the volumes required.
Closure planning and costing: A closure plan has been submitted, however, approval has not been
granted by the DME. It is understood that the lack of approval is due to internal bureaucracy, rather than
the DME having a material concern with the plan. Although, no approval has been given, Hlobane
is currently being closed, with closure activities being undertaken over the last seven years. It is expected
that closure work will be completed by 2015. Assuming that passive water treatment proves to be
successful on the industrial scale, the closure provision of ZAR49m for the mine is sufficient for the work
for which it has been allocated.
|