11.15
|
Heavy Minerals – Hillendale Mine
11.15.1 |
Compliance
An EMPR for Hillendale and Fairbreeze Project mining operations was approved by the DME on
10 March 1998. This approval includes an addendum to the EMPR dated 9 March 1998. An EMP
performance assessment undertaken in 2004 indicated that the Hillendale component of the EMPR
needed to be updated but that the Mine was generally compliant with its EMPR commitments. A revised
EMP was submitted to the DME before the end of 2005. In addition to the revised EMP, a social and labour
plan and mine works programme was prepared. The MPRDA conversion application was submitted to the
DME before the end of 2005.
No registrations for existing water uses have been submitted to DWAF, as the water uses generally
commenced in 2001 so do not fall under the NWA definition of existing uses. The Water Act, 1956, permit
for the use of industrial water was obtained for Hillendale in 1998. An application for a water uses licence
was submitted to DWAF in December 2004. To date no water use licence has been received from DWAF
so the Mine is theoretically operating illegally in terms of the NWA. As it is recognised that few water use
licences have been issued by DWAF for mining operations and an application has been submitted, the lack
of licence is not considered a major risk.
Due to the radioactivity associated with some of the mineral sands being extracted, the NNR has issued
COR 43 to cover radiation protection and monitoring at the CPC and Hillendale sites. The relevant
reporting requirements are being met.
There is an exemption from Section 20 of the ECA issued by DWAF, dated 8 June 2001, that allows for
the disposal of CPC wastes at Hillendale. This includes the gypsum deposited with slimes on the residue
deposit and the MSP and wet scrubber dust deposited in the mining void. Other disposal at Hillendale
is covered by the COR and the legal compliance audit (see below) indicates that clarity on the waste
disposal controls is required (this is currently being addressed by Ticor).
A legal compliance audit was undertaken in December 2004 for the Hillendale and CPC sites. It identified
a number of potential legal non-compliances. Kumba applied its risk rating criteria to the results of this
audit in June 2005 to identify the most serious legal risks, which included the water/EMP issues discussed
above and non-compliance with GN 704 (discussed further below). Ticor has set actions, responsibilities
and budget to address all the high level risks identified by Kumba. No additional risks or liabilities of a
material nature were identified during this review.
|
11.15.2 |
Environmental and Social Management
Environmental management at Ticor’s South African assets is handled by the Technical Services
Department. The Environmental and Radiation teams, reporting to the Technical Services Manager,
comprise five people. These teams handle environmental and radiation issues at both the Hillendale Mine
and the CPC at Empangeni. In addition, there is a rehabilitation officer who reports to the Hillendale
Mine Manager. Ticor SA has established an integrated quality control, environmental and occupational,
health and safety management system in accordance with the requirements of ISO 14001, ISO 9001 and
OSHAS 18001. Certification was obtained in December 2004. Ticor SA has a series of codes of practice
relating to various environmental and OSH issues. These are supported by standard technical procedures
for specific activities. All documents are electronically controlled using a document management system.
Community liaison and labour relations are generally managed by the Human Resources Department,
though some aspects may fall under the External Relations Manager. Ticor SA participates in a number
of community and environmental forums that are held either quarterly or six-monthly.
The operational environmental budget for Hillendale, CPC and some aspects of Fairbreeze Project is
ZAR1.0mpa, which covers environmental monitoring, consultancy fees, consumables and
donations/subscriptions to various organisations. The radiation department has a budget covering the same aspects of ZAR0.5mpa. The five year plan sees the budgets extending to ZAR1.7mpa and
ZAR0.8mpa, respectively. These are considered appropriate for the work being done. Remediation
budgets are covered elsewhere.
|
11.15.3 |
Environmental issues
Water management: The legal compliance audit expressed concern over compliance with GN 704 and
the water use licence application has not motivated for exemption from the requirements of these
regulations. To verify compliance and identify necessary actions, Ticor has appointed an external
consultant to undertake a detailed GN 704 audit (during September 2005). As ongoing water
quality/biological monitoring does not appear to indicate any significant impacts, it is expected that
motivation can be made for exemption from compliance with some of the regulations.
Rehabilitation: Ticor has committed to returning the land back to its previous status of sugar cane and
some subsistence farming. Currently, relatively large areas are disturbed (135Ha) though temporary
vegetation has been established to help in dust control (see below). A research project to determine how
best to re-establish the soil structure has recently been completed and the results are about to be field
tested. The test work is being done in consultation with stakeholders (e.g. South African Sugar Research
Institute) and will be externally monitored (a steering committee is being set up and will meet quarterly
to assess results). Once the optimal method has been determined, rehabilitation of the currently disturbed
areas will take place. Currently Ticor is setting aside ZAR100kpm for rehabilitation purposes, but this may
need to be increased once the test work is complete.
Dust: A number of complaints have been received from the surrounding communities regarding dust
arising from the exposed areas of the mine workings. A number of measures have been recently
(2004/2005) implemented to minimise the dust impacts, including planting of sugarcane or grass on the
kidney storage area, dune coating areas of the pit that are not actively being mined and use of
sprinklers/dust suppression chemicals in topsoil stripped areas. Ticor has indicated that dune coating can
result in 90% control efficiency of dust. Ongoing monitoring will indicate the effectiveness of these
measures, with daily monitoring taking place adjacent to the closest residential areas.
Radiation: Radiation management at the Mine falls under the requirements of COR 43, which is shared
with the CPC site (discussed further below). The level of radioactive material being deposited as a waste
material into the mine void is reportedly less than that being removed, resulting in an overall reduction
in radiation levels so no significant risk is envisaged. However, ongoing monitoring is taking place to
confirm this and it is recognised that radiation is an emotive issue to interested and affected parties.
Closure planning and costing: The EMPR includes some basic closure objectives and actions and
closure cost estimates have been prepared in the past. The most recent estimate (October 2004) used the
DME Financial Provision Guidelines as the basis for costing to give a closure cost of ZAR31.3m (includes
owner costs, contractors costs and 10% contingency). However, this assumes that only the final 40Ha
footprint will need to be rehabilitated as the rest will have been done as part of operational costs
(see above). It therefore does not necessarily reflect the cost to close the Mine with immediate effect. SRK
has concern that the DME Financial Provision Guidelines are generic in nature and do not reflect the
specific nature of individual operations. It is understood that Ticor SA will prepare a detailed closure plan
and cost estimate by the end of 2005. It is expected that the final closure cost will increase slightly but not
make a material difference to the operation.
|
|
11.18
|
Heavy Minerals – Tiwest JV
11.18.1 |
Environmental Management Systems
Each of the three Tiwest JV sites has an environmental management system certified to ISO 14001. The
environmental management systems of each site have been developed to meet the individual
requirements of the particular site to which it applies, though all seek to achieve continual environmental
improvement through similar processes.
Furthermore, the Kwinana site has its quality management system accredited to ISO 9001 standard.
Environmental targets are agreed to by the site management teams in order to meet policy commitments,
mitigate assessed risks, fulfil legal requirements, meet community expectations and improve performance
within the bounds of available resources. Targets are achieved through the implementation of
improvement projects in combination with an ongoing programme to improve operational procedures,
workforce awareness and commitment, accountability and emergency preparedness.
Furthermore, the Kwinana site has its quality management system accredited to ISO 9001 standard.
Environmental targets are agreed to by the site management teams in order to meet policy commitments,
mitigate assessed risks, fulfil legal requirements, meet community expectations and improve performance
within the bounds of available resources. Targets are achieved through the implementation of
improvement projects in combination with an ongoing programme to improve operational procedures,
workforce awareness and commitment, accountability and emergency preparedness.
|
11.18.2 |
Legislative Environment and Compliance
Commonwealth Approvals: Commonwealth approval is required if matters of national significance,
as defined in the Environmental Protection and Biodiversity Conservation Act, 1999, are triggered.
The Commonwealth Department of Environment and Heritage (“DEH”) is responsible for administering the
Act. Matters of national significance include presence of migratory birds, federally listed flora or fauna of
conservation significance, Commonwealth land, nuclear actions and marine areas. If matters of national
environmental significance are considered likely to be impacted, the project may be designated to be a
“Controlled Action” and Federal authorities will require formal environmental impact assessment to be
undertaken. The Commonwealth has entered into a Bilateral Agreement with the State of Western
Australia whereby State formal impact assessment procedures under the Western Australia Environmental
Protection Act, 1986, are accredited by DEH and the Commonwealth will not conduct a separate impact
assessment.
Western Australian Approvals: Within Western Australia, the Environmental Protection Act, 1986, and
the Mining Act, 1978, are the principal statutes defining the environmental management approval
processes and operating strategies of extractive activities and environmental protection within the State.
The Environmental Protection Act, 1986, makes provision for the establishment of the Environmental
Protection Authority (“EPA”), for the prevention, control and abatement of pollution and for the
conservation, preservation, protection, enhancement and management of the environment. The Act also
provides for the control and licensing of potentially polluting activities, land clearing, and is the Act under
which the State environmental approvals process operates.
Projects located on tenure granted under the Mining Act, 1978, are regulated by the Department of
Industry and Resources (“DoIR”). With regards to environmental management, the Act allows DoIR to play
an important role in the assessment of exploration and mining proposals, consultation with stakeholders
on environmental issues, and environmental compliance monitoring.
Environmental Approvals: Before commencement of any mining operation, a proponent is required,
under provisions of the Mining Act, 1978, to submit a Notice of Intent (“NOI”) to the DoIR. The NOI
describes the project, surrounding environment, potential environmental impacts and proposed prevention
and mitigation measures. Commitments made within the NOI are binding for any future operations on
these tenements unless a request for an amendment to the relevant government authorities is accepted.
Commitments typically relate to:
- Rehabilitation practices (topsoil removal and spreading);
- Closure criteria (waste dump slope angles, vegetation establishment success);
- Environmental management practices (dust control, chemical storage and handling);
- Environmental monitoring.
The DoIR, as the decision making authority for mining projects, is required under Part IV of the Environment
Protection Act, 1986, to refer mining projects to the EPA if they consider them likely to have a significant
effect on the environment. A Memorandum of Understanding exists between DoIR and the EPA whereby
projects are considered automatically to have significant effects on the environment if they satisfy the
criteria listed in Part IV (Environmental Impact Assessment) of the Environmental Protection Act, 1986.
EPA Approval: All projects referred to the EPA under Part IV of the Environmental Protection Act, 1986,
are assessed on a case-by-case basis. Once the EPA has received a referral, they assume responsibility for determining the appropriate level of assessment for the project. The Department of Environment
(“DoE”) provides technical assistance to the EPA to assist with this process. The level of assessment set
by the EPA will depend on environmental effects and the level of public interest associated with the
operation. Levels of assessment available to the EPA include nonassessment, informal review or formal
assessment. Differences between these levels of assessment relate to the public review period and the
detail of documentation required. The EPA may determine that no assessment is necessary if the referred
proposal is considered to have environmentally insignificant effects. Proposals considered not to warrant
assessment under the Environment Protection Act, 1986, are referred back to DoIR, who assess and
assign environmental conditions to the proposal’s tenement conditions upon approval of the environmental
documentation. The Water and Rivers Commission (“WRC”) (a department within DoE) administers
statutory processes of the Western Australia Rights in Water Irrigation Act, 1914. Groundwater Licences
and Licences to construct or alter wells are issued by the WRC.
DoIR Approval: If DoE makes no formal assessment, DoIR will issue approval on assessment of NOI
documentation. If DoE has made a formal assessment, DoIR will accept the assessment document
without the need for NOI documentation, although tenement conditions are likely to reference the
document and unconditional performance bond levels increased.
|
11.18.3 |
Existing approvals
Approval for all three sites for the Tiwest JV Joint Venture were granted through the Mineral Sands
(Cooljarloo) Mining and Processing Agreement Act, 1988. This Act essentially required prior owners of the
operations to submit a development proposal that included commitments and plans to safeguard
the environment (environmental management plan).
Amendments to each site have been made since the original approval. These have been gained
by submitting development proposals to the Minister for State Development. The Office of Major Projects
(“OMP”) has facilitated such proposals through the necessary regulatory authorities. Copies of these
development proposals have generally been submitted to authorities in the form of Notices of Intent
(“DoIR”), formal assessments (“DoE”) and Work Approvals (“DoE”).
Since July 2004, land clearing approvals are required to be obtained under the Environmental Protection
Act 1986 prior to any land clearing occurring. This change to legislation is likely to have significant impacts
on the ability to develop future mining operations in the Cooljarloo area as the area is characterised
by high biodiversity values. Key regulatory requirements for the mining and processing operations include:
- The Mineral Sands (Cooljarloo) Mining and Processing Agreement Act, 1988.
- Ministerial Statements of Environmental Approval issued under Part IV of the Environmental Protection
Act, 1986, including:
- Statement 37: Mine and Dry Separation plant (3/10/1988).
- Statement 50: Dry Separation Plant (12/12/1988).
- Statement 59: Synthetic Rutile Plant (28/2/1989).
- Statement 67: Dry Separation Plant – amendment to statement 50 (4/4/1989).
- Statement 412: Synthetic Rutile Plant – increased production to 200,000 tpa (4/4/1996).
- Statement 452: Pigment Plant (6/1997).
- Environmental Licences 5519/8 (Cooljarloo), 5939/8 (Chandala) and 5320/8 (Kwinana).
- Works approvals for significant process upgrades or modifications issued under Part V of the
Environmental Protection Act, 1986.
- Lease conditions on mining tenements ML268SA (Cooljarloo), M70/1010 (Cooljarloo).
- G70/165 – 168 (Chandala) and G70/88 – 90 (Chandala) issued under the Mining Act, 1978.
- Groundwater well licences issued under the Rights in Water and Irrigation Act, 1914.
|
11.18.4 |
Environmental compliance
Compliance with regulatory requirements is closely monitored by all sites. A programme whereby
environmental personnel from each site audit compliance of other sites has been implemented.
Regulatory inspections are undertaken by DoE and DoIR personnel. No serious non-compliances have
been reported as a result of these inspections. No non-compliances have occurred at the Cooljarloo mine
site in recent years. The volume of process wastes disposed of in onsite landfills if measured as wet
weight tonnes did exceed the licenced volume, however this was reported to regulatory authorities and an
increase in the licenced disposal volume was granted. Clarification is being sought by Tiwest JV to
determine if the licenced volume refers to wet or dry weight tonnes. The larger volume of waste resulted
from excavation of historically deposited materials in ponds at Chandala and Kwinana.
No non-compliances have occurred at the Chandala or Kwinana sites in recent years. One reportable
incident occurred at Kwinana during 2004 where loss of containment of sulphuric acid occurred from
a storage bund. The incident was investigated by DoE however no regulatory action was taken. Four
level 2 air emissions incidents occurred during 2004 with each reported in compliance with regulatory
requirements.
|
11.18.5 |
Environment, Closure and Rehabilitation Budgets
Cooljarloo: The operating budget for environmental management at the Cooljarloo site was AUD1.1m for
2005. A breakdown of this budget was reviewed and it appears suitable for requirements under the site
environmental licence.
In addition to this operating budget, allowance has been made within the life of mine physical and financial
plan for costs associated with vegetation clearing, topsoil clearing, land forming and rehabilitation on an
annual basis. Costs have been allocated until 2026 and vary in accordance with annual development and
rehabilitation rates. Forecast vegetation and topsoil stripping costs total AUD1.7m and AUD10.2m for the
period 2005 to 2026. Forecast land forming and rehabilitation costs total AUD17.1m and AUD26.1m,
respectively, for the period 2005 to 2026.
A rehabilitation provision account has been established for the operations with the provision currently
totalling AUD20m. The provision is increased by a predetermined rate per hectare of disturbance on
a monthly basis as areas are disturbed. Similarly the account is drawn down as areas are rehabilitated.
A separate closure provision of AUD3m has been established to address historic legacies. The financial
model includes allowances for rehabilitation and closure.
No rehabilitation bonds have been lodged for the Cooljarloo site. This is a direct result of the operations
being governed under a State Agreement Act. Discussions with regulatory authorities indicate that
placement of bonds on operations governed by State Agreement Acts is under review. Bonds may be
required to be lodged in line with DoIR guidelines in the medium to long term. Bonds are typically lodged
in the form of bank guarantees.
Kwinana: The operating budget for environmental management at the Kwinana site was AUD437,000 for
2005, and has been raised to AUD463k for 2006 (excluding salaries). A breakdown of this budget was
reviewed and it appears suitable for requirements under the site environmental licence. In addition to the
operating environmental budget, a waste management budget is set at between AUD1.7mpa to
AUD1.8mpa. This budget is for tipping fees for filter cake solid waste disposal at the Cooljarloo mine site
under licence. A provisional site closure and decommissioning plan has been completed and is estimated
at AUD12m. This figure is likely to rise as the budget has not been broken down to any level of detail as
yet. Financial provision for closure costs are the responsibility of the Joint Venture partners and Ticor has
provided for this in their financial statements in accordance with AIFRS.
Chandala: The operating budget for environmental management at the Chandala site in 2005 was
AUD86,000, including salaries. A breakdown of this budget was reviewed and it appears suitable for
requirements under the site environmental licence. In addition to the operating budget, Chandala had a
budget of AUD2.5m for solid waste disposal from the dry separator to the mine site, and AUD4.7m for
waste disposal from the synthetic rutile plant to the mine site. Waste volumes allowed for disposal are
limited by the mine site environmental licence, and determined by product throughput and grade.
At present, Chandala is operating at close to capacity and has no significant expansion plans, other than
debottlenecking improvements. The mine site recently had its landfill licence increased to accommodate
an additional 150ktpa, which is unlikely to be met under normal operating conditions at Kwinana and
Chandala. Chandala has recently developed a conceptual site closure and decommissioning plan, which
apparently includes a detailed cost estimate. This plan is presently being audited by a third party and SRK
were not granted exposure to it. As a result, SRK is unable to comment on the closure plan and associated
costs. As with the Cooljarloo Mine, Ticor has provided for this in its financial statements.
|
11.18.6 |
Environmental Issues and Risks
Cooljarloo: Rehabilitation progress has been severely constrained in years prior to 1999 resulting in the
operations having a larger amount of unrehabilitated land than would be desirable compared to industry
standards and regulatory expectations. One of the reasons for the large area disturbed is a result of slimes
management which requires large drying areas to be exposed. Rehabilitation is primarily required to return
land to native vegetation, however small areas located on Mullering farm are required to be rehabilitated
back to pasture. Discussions with site personnel indicate this has been recognised and additional funding
has been provided in recent years to reduce the historic legacy. This has included decommissioning five
of the six process waste cells present on site.
The amount of land disturbed, but not rehabilitated is expected to peak during 2005/2006 at about
1,700Ha and then decline thereafter. Required native vegetation closure criteria are presently being
established in consultation with regulatory agencies. Tiwest JV have recognised the challenge in being
able to establish criteria that are practical, achievable, measurable and acceptable to regulatory agencies.
Development in three new areas is being considered, namely Dongara, Jurien and Falcon.
Environmental approvals will need to be obtained prior to development commencing in these areas.
Review of information available for each of these areas indicates that approvals for mining in the Falcon
and Dongara areas are likely to be difficult due to high biodiversity values and presence of conservation
reserves. Formal assessment under the Environmental Protection Act, 1986, at a high level (Public
Environmental Review or Environmental Review and Management Plan) is considered the most likely
approval path. Difficulties have already been experienced in gaining land clearing approvals necessary to
allow further exploration. Extensive baseline studies will be required prior to development of environmental
impact assessment documentation.
Tiwest JV personnel are aware of the degree of difficulty likely to be experienced, the financial and
technical resources required and lengthy timelines likely to obtain approvals. Significant volumes of water
are required for dredging and ore processing operations. Difficulties have been experienced in sourcing
adequate water without causing adverse environmental impacts. Abstraction in the north mine borefield
caused unanticipated drawdown of the superficial aquifer and this in turn caused death of vegetation in
2000. Since dewatering of this aquifer ceased, water levels have returned to almost pre-abstraction levels
and vegetation has reportedly recovered.
To ensure similar incidents do not reoccur, Tiwest JV has commissioned extensive groundwater modelling
studies and installed two 600 metre deep bores in late 2004 to supply water for the north mine area.
As operations progress, the importance of reliable groundwater modelling will increase to ensure sufficient
water can be safely abstracted. Ongoing abstraction costs for the operation are likely to be high as a result
of the need to develop very deep bores.
A number of environmental monitoring programs have been developed and implemented for the
operations. These appear to address all potential environmental issues, are consistent with industry best
practice monitoring techniques and satisfy regulatory requirements. Results of monitoring are reported
annually in a publicly available report.
Chandala: The Chandala site undertakes a range of environmental monitoring programmes under its
Ministerial environmental licence (5939/8). The site is audited annually by DoE staff, and to date, has not
received any licence breaches. The site was next due for audit by DoE officials in November 2005.
Notwithstanding the DoE inspections, SRK believe that several issues should be brought to attention.
The dry mill stack on site is not licenced with the EPA. Tiwest JV are aware of this issue and are in the
process of addressing it. It is unlikely Tiwest JV will be held in breach of conditions and it appears
the issue is a simple oversight that both parties are presently rectifying.
There are two main environmental issues on site that pertain to potential and definite ongoing risk and
therefore liability. The first is the existence of several groundwater plumes beneath the site. There are
currently three distinct plumes from three separate sources. Two plumes are presently being managed
while the third is still being defined. A brief description of each groundwater plume is presented.
Plume 1 is located beneath the process liquor storage ponds adjacent to the waste water treatment plant
to the north of the plant. The plume was discovered in 1994, with the contaminants being ammonium and
sulphate. The plume source has largely been removed with decommissioning of one pond and double
lining of two others. Small leaks have since been detected on the relined ponds, though these are being
managed. The plume is being pumped and treated through extraction wells and sulphate and ammonium
levels have decreased from approximately 650 mg/L in 1994 to approximately 100 mg/L in 2004. It is
therefore reasonable to conclude that the plume has been captured and is presently under control, though
a leak remains and contamination remains in the groundwater.
Plume 2, which was discovered in 1996, is located below the synthetic rutile plant and is the result of poor
bunding and housekeeping methods. Tiwest JV are aware of the cause of the plume and are actively
managing it. The plume contains ammonium, sulphate (reduced from 4,000 to 1,000 mg/L since 1996) and
also has a low pH value of approximately 2.4 due to sulphuric acid leakage from the plant. Capital works
have been implemented to reduce point source contamination, in addition to remediating the groundwater
by pumping and treating through recovery bores and the waste water treatment plant. As with plume 1,
it is fair to say this plume has been contained and poses no immediate threats to off site waterways,
however, it remains in place and will therefore require remediating. In this sense the plume must be
considered a financial liability and risk. SRK believe that Tiwest JV are managing plumes 1 and 2
adequately, though current management methods must essentially be considered an operating cost. Once
plant is removed from site, the plumes should be relatively simple to remediate.
Plume 3 is located adjacent to, and down hydraulic gradient from the Brambles sub-contractor compound
near the site entry. It consists of low level hydrocarbon contamination from an unknown source. Tiwest JV
have received specialist advice suggesting they monitor, rather than treat the plume at present.
Contaminant levels are relatively low (<3.6 mg/L), though aquifer transmissivity is high, due to the sandy
nature of the soil and Chandala Brook is located relatively close to the plume. Tiwest JV are continuing to
receive advice in this regard and may commission an interception trench in due course.
Kwinana: The Tiwest JV Kwinana Pigment Plant is a designated major hazard facility due to the use of
chlorine on site. The plant is an aggregate of six smaller plants that each provides a stage in the
transformation of the synthetic rutile feedstock to the final product. The major environmental challenge at
Kwinana is arguably managing the chemical feedstock on site, which include chlorine, sodium hydroxide,
and natural, oxygen and nitrogen gases. Other environmental issues include managing waste products
from the various process stages. Hazardous gases produced on site are managed via flue gas incineration
and scrubbing, while waste water is treated and released under licence.
The plant operates under DoE environmental licence number 5320/8 and various legal Acts and
regulations. Licence 5320/8 allows the plant to expand to produce 180ktpa, up from the current 110ktpa,
if deemed viable. SRK identified the following as potential environmental issues and risks on site:
Managing operational incidents resulting in fugitive emissions of titanium tetrachloride (“TiCl4”) and
chlorine gas has been an historic issue on site. When exposed to water vapour present in the air, the TiCl4
hydrolyses releasing hydrochloric acid, titanium dioxide (TiO2) and heat. Tiwest JV have an incident
management plan in action for chlorine gas and TiCl4 release, with a level 3 incident being when a release
violates the site perimeter. Tiwest JV had no level 3 releases at Kwinana in 2003 or 2004, though it remains
a risk management issue should the plant expansion occur, simply as a function of increased throughput
and the proximity of industrial and residential premises.
An historic groundwater plume containing phenols is located immediately below the site footprint in a
relatively shallow aquifer (<20m). While Tiwest JV were not the source of this plume, rather, it originated
from a source offsite, a potential environmental liability may exist should draft Western Australian
Contaminated Lands legislation become law. It would be prudent for Tiwest JV to establish their legal
position in this regard. A second groundwater plume is located below the waste water treatment ponds
on site and is migrating towards Cockburn Sound. Tiwest JV are aware of this plume and believe that due
to the nature of the contaminants (sodium, sulphate and chloride), it is not an issue, as concentrations are
below those found in seawater.
Atmospheric emissions in the Kwinana industrial zone are managed under the Environmental Protection
(Kwinana) (Atmospheric Waste) Policy and Regulations (1999), whereby release volumes of individual
gases are established for each industrial facility. Relative latecomers to the Kwinana area have traditionally
found themselves with lower emission quotas than older, more established sites. In this regard, Tiwest JV
remain beneath their sulphur dioxide (SO2) limits, and are therefore not in breach of their environmental
licence. Tiwest JV have identified however, that the availability of their low sulphur (<1.5%) feedstock
petroleum coke is tightening, and therefore the price is likely to rise. Depending on management decisions
regarding the price sensitivity of low sulphur feedstock to their operations, a substitute option may include
higher sulphur (up to 5%) coke, at lower cost. This in turn, may at best result in increased caustic
consumption in post-emission incineration scrubbing units, and at worst, potentially increase SO2
emissions; depending on the efficiency of the vent stacks over time. These effects would be greater should
Tiwest JV choose to expand production at Kwinana.
These issues remain hypothetical at present, though ones that require consideration through appropriate
stoichiometric calculations. A solid waste product presently on site which is returned to the Cooljarloo mine
site for licenced, encapsulated disposal, contains low (<600 parts per billion) concentrations of uranium
and thorium. Presently, these concentrations are below threshold values in Western Australian legislation
that would otherwise deem the waste ‘radioactive’. As such, Tiwest JV are suitably licenced to handle this
product. If however, international standards that contain lower trigger values for both elements are
introduced into Australia, there is a risk that the products would become ‘radioactive’.
Implications should this occur include licensing, transport, and disposal. Furthermore, radioactive material
(albeit the same material presently located on site) is traditionally a sensitive community issue and there
may be community relations issues also involved. Again, this issue remains a hypothetical, however, Tiwest
JV would be best prepared by establishing contingencies and manage the risk accordingly.
As noted in the budgetary section of this environmental review, Kwinana has recently completed
a provisional site closure and decommissioning plan, with a budget estimated at AUD12m. Tiwest JV
recognise that this figure is likely to rise as more levels of detail are added to the plan. Financial provision
for the Kwinana site closure is provided for in Ticor’s accounts in accordance with AIFRS. Overall the
environmental staff at the Tiwest JV Kwinana site are pro-active and aware at managing their
environmental responsibilities suitably so that not only do they maintain an environmental licence, but
continually improve environmental management on site in accordance with ISO 14001 principles.
|
|