Environmental Issues
Rehabilitation of waste rock dumps: The waste rock contained in the 39 large waste dumps is inert,
non-acid forming, and other than suspended solids, does not produce a contaminated seep. Historically,
dumping was by end-tipping resulting in the creation of slopes at a natural angle of repose (37°). This slope
is difficult to rehabilitate as vegetation cannot easily traverse this slope. The DME may also consider them
to be potentially unstable. Furthermore, water runoff from the slopes leads to significant erosion. This has
been partially rectified via an internal directive to construct the dumps with a series of benches. Originally
bench widths were 20m, however this was increased to 30m in the 1990s and 45m in 2000. This has reduced
the overall slope angle, but slopes between benches are still at 37°. Low rainfall limits vegetation growth,
further hampering rehabilitation efforts. The Mine is currently experimenting with various rehabilitation options
including reducing slope angles and the inclusion of various soil ameliorants. Early indications are that the
difference in successful vegetation cover between a slope of 18° and 30° is minimal but the latter is
impractical as plants still have difficulty taking root on the slopes. Therefore, if the DME indicates that stability
is a problem, the Mine will re-profile the slopes to 24°. This slope angle allows vegetation to comfortably take
root, provide for adequate cover and reduce risks associated with stability. However, it still does not increase
the plant footprint to the extent that would occur if slopes were re-profiled to 18°. Currently, the Mine has no
provision for dump rehabilitation in its closure budget, as it is still awaiting the results of the vegetation
experiments. If it is determined that the slopes need to be cut back from the angle of repose, SRK estimates
that the rehabilitation will cost the Mine in the region of ZAR150 – 200m.
Backfilling of Pits: The EMPR commits the Mine to returning 50% of the waste rock to the pits at the end
of the life of mine. While the Mine is partially compliant with this commitment, a backlog has developed
as grade control dictates that the pit remains open as long as possible. This gives the Mine three options for
ongoing management: firstly, the mine plan will need to be revised to optimise ongoing operational backfilling;
secondly, motivation will need to be made to the DME on why backfilling is not practicable; or thirdly provision
in the order of ZAR100 – 150m will need to be included in the closure liability to backfill and rehabilitate the
final surface. As a final decision on how this will be managed has not been made, SRK has included this
provision as a sensitivity contingency.
Hazardous Material Handling: Historically, hydrocarbon housekeeping management has been poor
resulting in the contamination of the soils around the workshops, service and fuel stations and around the
High Energy Fuel (“HEF”) plant. To date the Mine has spent ZAR3m on rehabilitating the soils and it estimates that rehabilitation of the remaining contamination will amount to ZAR12m. It is expected that this will be
a once-off cost as oil handling has been improved through the implementation of new housekeeping
procedures.
Radioactive Sources: Some of the instrumentation in the plant is radioactive. These instruments are
managed by an operator licenced to handle radioactive sources. At the end of the life of the equipment, the
radioactive sources are disposed of by the Nuclear Energy Corporation (of South Africa). It is understood that
a provision for disposal has been made in the closure costing.
Water Contamination: No contamination, other than suspended solids is evident around the waste rock and
tailings dumps. Although, the Mine produces a relatively high sediment load, the lack of surface water in the
vicinity of the Mine means that the sediments drop onto surface where the runoff evaporates. The use of
explosive has led to slightly elevated nitrate levels around the waste rock dumps, however SRK understand
that these do not pose a significant risk. The plant utilises approximately 1Mm3/year of treated sewage
effluent during the washing process resulting in an effluent containing residual nitrates that is disposed on the
tailings dams. This has also resulted in a non-significant increase in nitrates in the groundwater above
background but still within DWAF’s drinking water guidelines. Groundwater in the vicinity of the hydrocarbon
spills is contaminated with hydrocarbons, however, migration of this plume is limited by groundwater
extraction ahead of mining. As the dewatering boreholes supplying town are a significant distance from the
source of contamination, there is a low risk that the town’s water supply will be contaminated.
Water Management: Sishen Mine is partially GN 704 complaint and has implement infrastructure to separate
clean and dirty water, where practical. Where not compliant, the Mine has either requested exemption or is
implementing management practices to become compliant. The majority of process water is sourced from the
dewatering boreholes with make up obtained from the sewage plant. When necessary, water is abstracted
from the Vaal – Gamagara pipeline. If there is a surplus, historically the Mine has discharged the portion not
supplied to the local towns, into a canal which flows towards the Gamagara River (Mine has permit to
discharge to the river). However, the water typically evaporates before it reaches the river. As the
contamination load in this water is low, it is not expected that the area where evaporation occurs has led
to significant soil contamination. The Mine has recently reached an agreement with DWAF, that any surplus
groundwater will be pumped to the Vaal – Gamagara pipeline.
De-watering: It has been determined that the Mine has created a de-watering cone that has extended
approximately 10km to the south of the Mine, impacting on local farmers water supply. This has resulted
in the Mine now being required to supply one farmer with a tank full of water on a daily basis and to pay the
difference in costs between abstracting groundwater and pumping water from the Vaal – Gamagara pipeline
for another farmer. The Mine has an agreement that it will assist the remaining three farmers “as and when
required” (although, there does not seem to be a definition of ‘as and when required’). The Mine is
investigating whether a dewatering plume has developed on the northern and western side of the Mine
(studies indicate that there is no de-watering cone on the eastern side as it is limited by a significant dyke).
Given that the groundwater in the vicinity of the Mine is relatively compartmentalised, the geology of the
northern and western side indicates a low potential for the development of a significant dewatering cone.
Soil Contamination: Aside from the areas contaminated by hydrocarbons, the Mine reports that the soils
around the ammonia nitrate stores have been contaminated during product handling and from spills and
accidents. The area is relatively small and does not represent a significant liability.
Sinkhole Formation: The dolomites underlying the ore body have the potential to form sinkholes. Mining
activities have opened a large sinkhole in the South Pit that requires backfilling during the mining process.
The Mine has not undertaken any geotechnical investigations to determine areas of potential sinkhole
formation, however, Sishen is aware of exploration drilling core losses indicative of potential sinkhole
formation. These potential sink holes are relatively small and are all within the mining area. Therefore, aside
from a safety risk, these sinkholes do not pose a risk to the surrounding communities.
Waste Handling: Historically the Mine has operated a domestic waste dump in the Mikrogolf area. This dump
has recently been permitted by DWAF, however, the Mine is in the process of closing the dump, as the space
is needed for the disposal of waste rock. It is not foreseen that there will be any problems with this closure
plan, although the Mine will have to obtain closure in terms of Section 20 of the ECA.
Air Emissions: Dust emissions from the Mine are currently a nuisance to the local community with dust being
generated in the pit, on haul roads and in the plant. The Mine has implemented dust control measures, such
as the use of hydrophilic chemicals at the crushers and Dust-a-Side on the haul roads. With appropriate
management this does not pose a significant risk.
Community Relationships: Sishen has finalised its social and labour plan. The Mine operates two
community development projects that are expected to become sustainable in time. The first is the employment of redundant farm workers to remove an intruder plant from the Mine and the surrounding Ferroland farms.
Sishen has supplied equipment and training to the farm workers. The wood is used to manufacture charcoal,
while the wood chips are sold to the Mine for use as organic material during the rehabilitation of the dumps.
The second project is the establishment of the Tshipi development centre in conjunction with the Department
of Labour. Tshipi focuses on equipping members of the local community (as well as members of the Defence
Force and Correctional Services) with a trade skill. A portion of the profits generated by those trained is
channelled back to the centre.
Closure Planning and Costing: Closure planning is limited to that covered by the EMPR. The Mine has
estimated its liability for immediate closure to be ZAR196m. SRK is of the opinion that the provision is
adequate for the work for which it is allocated. This does not allow for any provision for rehabilitation of the
waste rock dumps, nor for backfilling 50% of the pit (see above).
|