8.1
|
Introduction
This section includes discussion and comment on the infrastructure-related aspects necessary for the execution
of the LoM Plans associated with the Material Properties. Specifically, real capital requirements at 1 January 2006
are provided based on estimation, adequacy of design and project development schedules. A general discussion
on power generation and distribution, water sourcing, reticulation and planned maintenance programmes is included
in Section 8.2. Specific discussion on capital expenditure requirements is included in Section 8.4.
|
8.2
|
Engineering infrastructure of the Material Properties
Engineering infrastructure at the Material Properties includes a wide range of operating technologies The level
of supporting infrastructure and services is dependent on the location of the operation in relation to industrial centres
and major access routes.
Underground mining operations comprise access infrastructure to convey personnel, materials and equipment
to and from the working areas and associated services to support mining operations. Surface access infrastructure
primarily includes declines. Horizontal access infrastructure include, crosscut haulages, footwall haulage levels,
declines/inclines and cross-cuts. Associated underground infrastructure includes ore passes, conveyor belts,
crushing stations, ore bins, loading stations, water dams, pump stations, secondary ventilation plants, workshops,
and power and water reticulation systems. Associated surface infrastructure includes primary ventilation fans, office
blocks and training centres, workshops and stores, lamp rooms, change houses and accommodation. At the Material
Properties there are also a number of service and supply centres. These include compressed air supply stations, and
major workshops for repair of major plant and equipment.
Surface mining operations are typified by their high degree of mechanisation and relatively high productivity
in comparison with their underground counterparts. Access and service infrastructure at Exxaro’s open-pit operations
reflect their scales of operation and location to primary access routes. In all instances however, these are based
on the typical requirements for open-pits utilising conventional earthmoving equipment and include primary crushing
facilities, RoM and product stockpiling facilities, waste dumps, consumable storage facilities, power generation and
reticulation, water storage, workshops, mine offices and accommodation, airstrips and auxillary infrastructure
buildings.
Notwithstanding the age of the general infrastructure, SRK consider that all surface and underground infrastructure
is reasonably maintained and equipped. In conjunction with planned maintenance programmes, including specific
remedial action and expenditure of projected ongoing capital allowances, the current infrastructure is considered
by SRK to be adequate to satisfy the requirements of the LoM Plans.
Further, the power generation and distribution systems, water sourcing and reticulation systems are appropriate for
operations as envisaged in the individual LoM Plans. Where this is not the case SRK has allocated appropriate capital
costs, which have been included in the TEPs presented in Section 13.
|
8.3
|
LoM Capital Expenditure Programmes
The following section gives, where appropriate specific comments on the status of the underground and surface
infrastructure, in addition to a breakdown of the total capital requirements of the current LoM Plans. Distinction is
made between project capital and on-going capital, whereby project capital encompasses all major items identified
for the LoM period. On-going capital is considered to be a provision, based on a historical percentage of operating
costs incorporating appropriate modifications for the last two years of operations, thus recognising that as the
operation approaches closure capital expenditure will decline.
Table 8.1 and Table 8.2 provide the latest project and on-going capital requirements for the Material Properties and
regional infrastructure requirements excluding off-mine exploration costs. In preparing the tables the following apply:
- Where appropriate SRK have included additional infrastructure as identified in Sections 5 through to Section 7;
- All capital amounts are exclusive of financing charges and separation costs and unless otherwise stated are
considered by SRK to be adequate to meet the requirements of the current LoM Plan;
- The statistical estimate class currently reflects a typical accuracy level of a Class I at –15% to +25%.
- A contingency amount is applied only to the project capital component; and
- Unless otherwise stated all amounts are not attributable and reflect 100% contributions.
|
8.4
|
Material Properties
Capital expenditure requirements for the Material Properties are principally aimed at, development projects,
expansion projects, mobile fleet replacement, metallurgical plant modifications, installation of tailings dam facilities and
infrastructure rehabilitation programmes and other ongoing capital. The total estimated capital expenditure for the
Material Properties is provided in Table 8.1. The principal components of the current project capital include the
following:
- Iron Ore
- At Sishen Mine the capital expenditure required for the SEP includes crushing, screening, beneficiation utilising
jig technology, product handling and load out utilising the existing facility;
- The Sishen South Project requires capital for crushing, screening, beneficiation utilising jig technology, product
handling and load out utilising a new facility;
- Coal
- Capital expenditure requirements for the all the operating Coal assets are aimed at ongoing capital and new
projects;
- Heavy Minerals
- At the Hillendale mine strategic development capital expenditure and replacement capital expenditure for the PWP
and the MSP;
- The development of the Fairbreeze Project C and Fairbreeze Project C Extension deposits including the erection
of a PWP at the Fairbreeze Project area and the establishment of a slimes dam storage facility to service the
Fairbreeze Project area;
- The development of the Block P deposit and the establishment of general infrastructure at the Block P mining
area, infrastructure to pump mined heavy mineral sands from Block P mining area to the PWP at Hillendale Mine;
- At the CPC smelter site sustaining capital expenditure and reline capital expenditure;
- At the CPC smelter site capital expenditure for support services;
- At the CPC smelter site capital expenditure for support services;
- Base Metals
- At Rosh Pinah there are no major capital projects other than completion of the various plant modifications
as currently underway, mobile fleet equipment replacement and ongoing capital provisions; and
- At Zincor the major short-term capital project is the building of a new waste disposal facility as mentioned
in Section 7; and
- Industrial Minerals
- At Glen Douglas Mine there are no major capital projects.
| Table 8.1 Estimated Real Capital Expenditures Scenario I |
| Material Property |
|
Sustaining |
|
Project |
|
Total |
|
| |
|
Capital |
|
Capital |
|
Capital |
|
| |
Units |
Real |
|
Real |
|
Real |
|
| Iron Ore |
|
|
|
|
|
|
|
| Sishen Mine(1) |
(ZARm) |
6,968 |
|
4,014 |
|
10,982 |
|
| Sishen South Project |
(ZARm) |
288 |
|
860 |
|
1,148 |
|
| Thabazimbi Mine |
(ZARm) |
69 |
|
|
|
69 |
|
| |
|
|
|
|
|
|
|
| Coal |
|
|
|
|
|
|
|
| Grootegeluk Mine |
(ZARm) |
3,121 |
|
|
|
3,121 |
|
| Leeuwpan Mine |
(ZARm) |
776 |
|
|
|
776 |
|
| Tshikondeni Mine |
(ZARm) |
210 |
|
|
|
210 |
|
| Arnot Colliery |
(ZARm) |
491 |
|
|
|
491 |
|
| Matla Colliery |
(ZARm) |
2,183 |
|
|
|
2,183 |
|
| New Clydesdale Colliery |
(ZARm) |
61 |
|
76 |
|
137 |
|
| North Block Complex |
(ZARm) |
12 |
|
20 |
|
32 |
|
| Sintel Char Project |
(ZARm) |
43 |
|
152 |
|
195 |
|
| Inyanda Project |
(ZARm) |
63 |
|
194 |
|
257 |
|
| Mafube JV Phase II Project |
(ZARm) |
188 |
|
2,000 |
|
2,188 |
|
| Belfast Project |
(ZARm) |
70 |
|
118 |
|
188 |
|
| Ingcambu Project |
(ZARm) |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| Heavy Minerals |
|
|
|
|
|
|
|
| Hillendale Mine and Fairbreeze Project |
(ZARm) |
1,104 |
|
545 |
|
1,649 |
|
| Ticor Smelter |
(ZARm) |
1,714 |
|
347 |
|
2,062 |
|
| Tiwest JV |
(AUDm) |
681 |
|
|
|
681 |
|
| |
|
|
|
|
|
|
|
| Base Metals |
|
|
|
|
|
|
|
| Rosh Pinah |
(NADm) |
34 |
|
|
|
34 |
|
| Zincor |
(ZARm) |
1,332 |
|
|
|
1,332 |
|
| Chifeng |
(RMBm) |
410 |
|
276 |
|
686 |
|
| |
|
|
|
|
|
|
|
| Industrial Minerals |
|
|
|
|
|
|
|
| Glen Douglas |
(ZARm) |
310 |
|
|
|
310 |
|
| Kumba Ferroalloys |
(ZARm) |
48 |
|
|
|
48 |
|
| (1) Includes SEP Phase I. |
|
|
|
|
|
|
|
| Table 8.2 Estimated Real Capital Expenditures Scenario II |
|
| Material Property |
|
Sustaining |
|
Project |
|
Total |
|
| |
|
Capital |
|
Capital |
|
Capital |
|
| |
Units |
Real |
|
Real |
|
Real |
|
| Iron Ore |
|
|
|
|
|
|
|
| Sishen Mine(1) |
(ZARm) |
6,968 |
|
4,014 |
|
10,982 |
|
| Sishen South Project |
(ZARm) |
288 |
|
860 |
|
1,148 |
|
| Thabazimbi Mine |
(ZARm) |
69 |
|
|
|
69 |
|
| |
|
|
|
|
|
|
|
| Coal |
|
|
|
|
|
|
|
| Grootegeluk Mine |
(ZARm) |
5,174 |
|
|
|
5,174 |
|
| Leeuwpan Mine |
(ZARm) |
776 |
|
|
|
776 |
|
| Tshikondeni Mine |
(ZARm) |
210 |
|
|
|
210 |
|
| Arnot Colliery |
(ZARm) |
491 |
|
|
|
491 |
|
| Matla Colliery |
(ZARm) |
2,183 |
|
|
|
2,183 |
|
| New Clydesdale Colliery |
(ZARm) |
61 |
|
76 |
|
137 |
|
| North Block Complex |
(ZARm) |
12 |
|
20 |
|
32 |
|
| Sintel Char Project |
(ZARm) |
43 |
|
152 |
|
195 |
|
| Inyanda Project |
(ZARm) |
63 |
|
194 |
|
257 |
|
| Mafube JV Phase II Project |
(ZARm) |
195 |
|
2,000 |
|
2,195 |
|
| Belfast Project |
(ZARm) |
70 |
|
118 |
|
188 |
|
| Ingcambu Project |
(ZARm) |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| Heavy Minerals |
|
|
|
|
|
|
|
| Hillendale Mine and Fairbreeze Project |
(ZARm) |
1,104 |
|
545 |
|
1,649 |
|
| Ticor Smelter |
(ZARm) |
1,714 |
|
347 |
|
2,062 |
|
| Tiwest JV |
(AUDm) |
681 |
|
|
|
681 |
|
| |
|
|
|
|
|
|
|
| Base Metals |
|
|
|
|
|
|
|
| Rosh Pinah |
(NADm) |
34 |
|
|
|
34 |
|
| Zincor |
(ZARm) |
1,332 |
|
|
|
1,332 |
|
| Chifeng |
(RMBm) |
410 |
|
276 |
|
686 |
|
| |
|
|
|
|
|
|
|
| Industrial Minerals |
|
|
|
|
|
|
|
| Glen Douglas |
(ZARm) |
310 |
|
|
|
310 |
|
| Kumba Ferroalloys |
(ZARm) |
48 |
|
|
|
48 |
|
| |
|
|
|
|
|
|
|
| (1) Includes SEP Phase I. |
|
|
|
|
|
|
|
|