Chifeng
The nominal design capacity of the Chifeng smelter originally was 21ktpa slab zinc with 36ktpa sulphuric acid.
Since 1998 the smelter has consistently exceeded the design capacity for both zinc slab and sulphuric acid
production. The capacity of Phase I is now stated to be 23.5ktpa zinc. This highlights the robustness of the
chosen process, which is supported by an original conservative design.
Baiyinuoer Mine started with the construction of a roaster and sulphuric acid plant at Lindong. With the
intervention of Kumba this facility was taken over to form part of Chifeng.
The Lindong design as proposed by the Yangzhou Chemical Engineering Company is conservatively based
on producing the equivalent of 30ktpa of contained zinc in calcine and 47ktpa of sulphuric acid.
Roasting: Concentrate roasting is performed via fluidized bed roasters roasting according to the standard
ENFI design, or variants of it, and the Lurgi fluidised bed roaster concept. The major difference in the above
roasting concepts being in the hearth and tuyere design, where the ENFI concept makes use of a bubble cap
design whilst the Lurgi design makes use of small annular perforations in the bed of the hearth. All the
concepts however basically adhere to the fluidisation velocity criterion for zinc concentrates of 0.4 – 0.7m/s
in the hearth area, and 0.25 – 0.4m/s in the freeboard zone. The above figures imply air rates per hearth area
of between 500 and 550Nm3/m2/hr. Typical dry solids design throughputs for ENFI roasters are 5.5 dry
t/m2/day, which for the latter air fluidising rates equates 90 to 100 dry t/Nm3 air.
Zinc concentrate roasting for Chifeng and Lindong is preferentially conducted at temperatures in the region
of 870º – 920ºC. This is a precautionary step governed by the high silica levels of the concentrates treated.
Temperature control is executed by cooling coils and feed control. As a backup plan and when problems
occur, direct water injection into the bed is used. At the fluidising air rates and operating temperatures that
the roasters operate at, the typical ratio of calcine to bed material discharge is 60% – 65% and calcine to
fume dust carryover to waste heat boiler are between 40% – 35%.
Fume/Particulate removal from the gas stream exiting the roaster is executed via conventional methods.
Coarser particulates are first recovered in the waste heat boiler, cyclones and electrostatic precipitators. Finer
air-borne particulates are scrubbed from the gas in a humidifying tower or venturi-scrubber, followed by a gas
cooling tower and electric demister (mist precipitator). In this gas scrubbing circuit a weak acid solution is
continuously circulated across the humidifying/venturi-scrubber and gas cooling towers to prevent solid and
impurity carry-over to the sulphuric acid. This circulating weak acid stream undergoes heating in the process
and requires to be cooled with cold water through a plate heat exchanger. A constant weak acid bleed stream
is removed to the wastewater treatment plant in order to control a build-up of impurities.
Calcine Handling: For both Chifeng and Lindong the roaster calcine has to be cooled before being
transferred to a storage or loading facility.
The process typically consists of cooling of roaster bed calcine in a water-cooled cooling drum before it is
transferred to a pneumatic transfer vessel, in the case of Chifeng, and to a storage shed in the case of
Lindong. The calcine/fume recovered in the waste heat boiler, cyclone and electrostatic precipitators is
collected and conveyed via redler/conveyors to a common collecting water-cooled redler conveyor. All
conveyors are enclosed units in order to prevent material spillages and losses.
At the Lindong site calcine is conveyed to a covered storage facility where it is bagged and loaded onto trucks
for transport to the Chifeng site. On arrival at the Chifeng site the trucks are offloaded via an overhead crane
and the bagged calcine stored in a new storage shed ahead of the main calcine storage silos.
The calcine collected from the Chifeng roasting facility is pneumatically transferred to the main calcine
storage silos at the head of the leaching section, whilst the Lindong calcine is first emptied and milled in a
dedicated milling circuit before being pneumatically conveyed to the same common calcine storage silos.
From the main storage silos the Chifeng and Lindong calcine mix is transferred to intermediate calcine
storage silos located within the leach building from where it is added normally only at neutral leach stage and
sometimes to stabilise the process also at the pre-neutralisation stage.
Acid Production: Acid production typically follows the double contact – double absorption process across a
converter with vanadium pentoxide catalyst beds. A variant of this process is a possibility where a triple
contact – double absorption system may be adopted. In the latter, the gas passes through three beds of V2O5
catalyst (versus two for the former) before passing through the inter-pass absorption tower. From the inter
pass absorption tower the gas then passes through two beds of catalyst before being contacted with 98%
H2SO4 in the final absorption tower.
Gas temperatures into the converter are maintained at the required and optimum temperatures for SO2 conversion by contacting hot and cold gas streams counter currently in insulated vertical shell and tube heat
exchanger arrangements. For cold start-ups an in-line electrical primary pre-heater is found in the ducting
prior to the first entry point of the converter. This pre-heater is assisted by a secondary pre-heater to aid falling
gas temperatures prior to entry of the last two contacting stages. The secondary pre-heater is generally also
utilised for cold start-ups but may also be required during normal operations to raise falling converter
temperatures.
Air and gas transport across the roasting to contact sections of the acid plant may be accomplished by
various blower/fan arrangements. Typically a “push-pull” concept is adopted across the gas-train with the
roaster blower “pushing” and an intermediate fan located prior to the contacting section of the Acid plant
“pulling” the gas through the waste heat boiler, electrostatic precipitator and gas scrubbing sections and then
“pushing” it on to the contact plant. This operation may be conducted with a roaster blower working either in
tandem with a hot gas fan (located after the electrostatic precipitator) and a main SO2 blower located in front
of the contacting circuit (drying tower), or only with a main SO2 blower (without a hot gas fan). Only a main
SO2 blower without a hot gas fan in both current acid plants is used.
Leaching: Leaching of the calcine is conducted using the conventional neutral leach and hot acid leaching
stages with an intermediate pre-neutralisation step located between the two for acidity control prior to iron
precipitation.
The Chifeng process operates a neutral leach at typical pH levels encountered in the industry. Its single hot
acid leach differs from the norm in that is a single step operating at moderate terminal acidities (60 – 80 g/l
H2SO4) and temperatures (80º – 85ºC).
The main reason for this is to prevent unmanageable circulating loads of silica building up within the leach
circuit due to the high silica input from the raw materials. Furthermore this operating regime requires very little
to no calcine addition to the pre-neutralisation stage for acidity control. The lack of process control and
instrumentation complicates the operation of this pre-neutralisation stage and periodically leads to
troublesome physical liquid/solid separation and throughput problems.
A secondary reason the chosen flow sheet is pursued is that there is no need to upgrade the Pb/Ag residue
for silver recovery, as the silver input in raw materials is low. A slight sacrifice in zinc extraction is made at the
option of operating a more forgiving and operator friendly circuit. At this stage the option of expanding the hot
acid leaching stages is not justified as the operating costs and process throughput problems will outweigh the
potential extra zinc recovery.
Iron Removal: Iron removal is in the form of ammonium jarosite based on the low contaminant jarosite
process proposed in the late 1970s by Electrolytic Zinc Australia (Pasminco). The low contaminant claim
comes from the fact that no calcine is added to the stage during iron precipitation, hence the precipitate
should be very low in contaminants such as zinc, cadmium, copper and lead. Trace levels of heavy metal
contaminants would then be associated with co-precipitated species and occluded soluble species.
The Chifeng process makes use of ammonium hydro carbonate as the source of alkali for both acid
neutralization as well as ammonium jarosite precipitation and operates the process as close to 95ºC as
possible and within the prescribed acidity levels.
The process operates smoothly with the required amount of iron being removed easily within the prescribed
residence time. An easily filterable product is produced at the end of the reaction period.
The major weakness the process suffers from is the precipitate contamination caused though solids carryover
in the preceding pre-neutralisation stage.
Purification: Purification technology adopts a batch purification technique for the removal of copper and
cobalt with traces of nickel in a common precipitate, followed by cadmium removal in low-grade cement. For
the removal of cobalt the process adopts the hot zinc dust/arsenic technique with the arsenic being added as
sodium arsenate after dissolving arsenic trioxide with caustic soda solution. In the cadmium scavenging
process, zinc dust additions are made together with copper and ferrous sulphate, and potassium
permanganate solution. The emphasis in the batch processing approach is placed on the ability to produce
a first-pass high quality solution with extremely low levels of cobalt and cadmium. This quality comes at a high
price in terms of reagent consumptions – particularly zinc dust powder. The lack of proper process control
together with the high zinc dust dosage renders low-grade primary cakes in terms of cobalt, copper and
cadmium. These primary cakes also contain high levels of basic and metallic zinc salts. Both the primary
purification cakes undergo a mild acid leach/wash to recover the bulk of the zinc as well as to upgrade the
by-product metal contents in a subsequent secondary treatment outside of the main process flow for zinc
production.
By-Products Production: The by-products production process entails the production of three upgraded
products of which two can be sold (containing copper and cobalt), and the third (cadmium), which is
stockpiled. In the treatment process the combined primary purification filter cakes are firstly exposed to a
mildly acidic leach/wash, which renders most of the cadmium and cobalt soluble but leaves the bulk of the
copper precipitate intact. The solids recovered from this first stage represent the upgraded copper residue. In
subsequent processing the dissolved cadmium is first cemented out with zinc dust powder under controlled
zinc dust additions to yield high-grade cadmium cement. This step is followed by the controlled precipitation
of the dissolved cobalt with arsenic trioxide and zinc dust powder to produce an upgraded cobalt residue.
Electrowinning: In the process of electrolysis, standard industry operating techniques are generally used
within a cell house operating with a 24-hour plating cycle with manual cathode stripping. A conservative
design in terms of operational current density is applied upfront.
The cell house configuration adopts tight cell electrode packing with small inter-electrode gap, which enables
the operation to take full advantage of low electrolyte resistances and resultant low cell voltages and power
consumption. There are two tank houses with two banks each of 57 cells containing 46 cathodes and
47 anodes. The current efficiency is 86%.
Casting: Casting of the zinc cathode into zinc slab adopts standard induction furnace and continuous casting
belt technology.
Zinc Metal Supply: There are currently 25 different mines supplying concentrate to Chifeng. No formal toll
treatment contracts are in place. There is a format on which payment is made. The compensation to each
mine is negotiated every month. Based on current market conditions, a base line zinc price equivalent to
±65% of the zinc price is determined. Concentrates with >50% zinc content are fully compensated for with a
RMB20/t deduction for every 1% below 50%. For concentrates containing 45% and less zinc RMB50/t is
subtracted for every 1% less than 45% zinc. Concentrates containing 40% and less zinc are generally not
accepted but if accepted RMB100/t is subtracted for every 1% less than 40% zinc. A penalty is imposed for
CaO content of more than 0.5% at a rate of RMB60/t.
|