Sishen Mine and SEP
Sishen Mine: The original ore handling plant at Sishen Mine was a dry crushing and screening plant
commissioned in 1953. In 1963, the first dense medium separation (“DMS”) plant, South Plant, was
commissioned. The North Plant, with a design capacity of 18Mtpa, was commissioned in 1976. In 1984, it
was decided to rationalise production and the South plant was shut down.
Four types of hard high-grade ore are presently mined from the Sishen pit, namely massive, laminated,
conglomerated and brecciated iron ore. The supply to the primary crusher of a suitable mixture of RoM ore
largely controls the chemical quality of the final products. Presently only material with an iron content of
greater than 60%Fe is fed to the plant.
Open pit ore is crushed via a primary gyratory crusher and two secondary cone crushers ahead of primary
stockpiling. A smaller in-pit gyratory crusher is also available as required. Ore is withdrawn from the primary
stockpile and sized into various fractions by washing and screening. Ore in the size range –90+25mm is
beneficiated in the coarse dense medium (“DM”) drum plant. This circuit also includes a Larcodem dense
medium vessel. Ore in the size range –25+8mm is beneficiated in the medium DM drum plant. Fine ore is
split into two size fractions, –8+5mm and –5+2mm ahead of beneficiation in the coarse and fine DM cyclone
plants, respectively. The –2+0.2mm fraction is forwarded to a new up-current classifier circuit for beneficiation.
Product from the coarse drum plant undergoes quaternary crushing and screening to meet product size
specifications, whilst the other circuits are correctly sized ahead of beneficiation. In total five products are
produced:
- Sishen 66%Fe 27mm Direct Reduction Ore;
- Sishen 66%Fe 25mm Lumpy Ore;
- Sishen 66%Fe 20mm Lumpy Ore;
- Sishen 65%Fe 8mm Coarse Sinter Ore; and
- Sishen 65%Fe 5mm Fine Ore.
Dense medium rejects are stored on waste dumps whilst slimes are stored in tailings dams.
Capacity at the North Plant has been steadily increased to the current capacity of 28 to 29Mtpa.
Considering its age, the plant appears to be in a fair condition, both mechanically and structurally. With normal
preventative maintenance and continuation of the refurbishment programmes already initiated, the plant can
be expected to operate for the period scheduled in the LoM Plan.
Key historical processing statistics for the Sishen Mine Process Facility are summarised in Table 6.1.
| Table 6.1 Sishen Mine: Main Plant Operating Statistics |
|
|
Description
|
Units
|
2001(F)
|
|
2002(F)
|
|
2003(H2)
| |
2004(C)
|
|
2005(C)
|
|
2006(C)
|
|
|
Headfeed
|
(Mt)
|
30.9
|
|
32.0
|
|
16.3
|
|
32.8
|
|
31.8
|
|
33.5
|
|
|
Product
|
(Mt)
|
26.3
|
|
26.8
|
|
13.5
|
|
27.5
|
|
28.8
|
|
29.0
|
|
|
Proportion Fine
|
(%)
|
33
|
|
32
|
|
31
|
|
30
|
|
31
|
|
33
|
|
|
Plant Yield
|
(%)
|
84
|
|
82
|
|
83
|
|
85
|
|
89
|
|
82
|
|
|
(F) |
Financial Year ended 30 June.
|
|
(H2) |
Six months ended 31 December due to the change of Financial Year.
|
|
(C) |
Calendar Year ended 31 December.
|
The LoM Plan assumes an average RoM throughput of approximately 32.4Mtpa. The LoM yield is projected
at an average of approximately 88% to yield total product of 29Mtpa. This is in line with current performance
but somewhat higher than that achieved in recent years. The current performance has principally been
ascribed to improved ore definition and the implementation of selective mining.
Average product quality achieved in recent years is summarised in Table 6.2.
|
Table 6.2 Sishen Mine: Main Plant Product Qualities |
|
|
Description
|
Units
|
Fe
|
|
SiO2
|
|
Al2O3
|
|
K2O
|
|
P
|
|
Oversize
|
Undersize
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Max
|
Max
|
|
|
27mm DR Ore
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2004 2005 Average
|
(%)
|
66.35%
|
|
2.92%
|
|
1.20%
|
|
0.12%
|
|
0.054%
|
|
10.6%+27mm
|
4.3%13mm
|
|
|
Current Specification
|
(%)
|
66.00%
|
|
3.70%
|
|
1.50%
|
|
0.16%
|
|
0.057%
|
|
15.0%+27mm
|
5.0%13mm
|
|
|
25mm Lump Ore
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2004 2005 Average
|
(%)
|
66.30%
|
|
2.90%
|
|
1.22%
|
|
0.13%
|
|
0.055%
|
|
6.4%+25mm
|
4.1%8mm
|
|
|
Current Specification
|
(%)
|
66.00%
|
|
3.70%
|
|
1.50%
|
|
0.16%
|
|
0.057%
|
|
7.5%+25mm
|
5.3%8mm
|
|
|
20mm Lump Ore
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2004 2005 Average
|
(%)
|
66.33%
|
|
2.88%
|
|
1.23%
|
|
0.13%
|
|
0.055%
|
|
8.2%+20mm
|
6.2%8mm
|
|
|
Current Specification
|
(%)
|
66.00%
|
|
3.70%
|
|
|
|
|
|
0.057%
|
|
20.0%+20mm
|
9.0%8mm
|
|
|
8mm CS Ore
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2004 2005 Average
|
(%)
|
65.85%
|
|
3.14%
|
|
1.40%
|
|
0.16%
|
|
0.057%
|
|
18.6%+8mm
|
8.5%5mm
|
|
|
Current Specification
|
(%)
|
65.00%
|
|
4.20%
|
|
2.00%
|
|
0.24%
|
|
0.066%
|
|
22.0%+8mm
|
16.0%5mm
|
|
|
5mm Fine Ore
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2004 2005 Average
|
(%)
|
65.49%
|
|
3.28%
|
|
2.08%
|
|
0.19%
|
|
0.061%
|
|
6.5%+5mm
|
7.0%0.2mm
|
|
|
Current Specification
|
(%)
|
65.00%
|
|
4.20%
|
|
2.00%
|
|
0.24%
|
|
0.066%
|
|
8.4%+5mm
|
12.0%0.2mm
|
|
It is evident that all other specifications have generally been met in recent years.
Sishen Expansion Project: Feed to the existing beneficiation plant is restricted to material with a grade of
greater than or equal to 60% beneficiated Fe in order to meet the required product specifications. Included in
Sishen’s growth strategy is the implementation of the brown field Sishen Expansion Project (“SEP”) aimed at
beneficiating lower grade material in the range of 45% in situ Fe to + 60% in situ Fe to saleable product quality.
This results in a significant increase in resource base and utilisation thereof.
Due to high separation densities required to beneficiate such material, DMS as currently employed at Sishen
is not a suitable technology. Jigging however, is a viable option and a feasibility study incorporating this
technology was completed in January 2005. Project start up is planned for July 2007, with capacity of 10Mtpa
saleable product being realised by June 2008 and a further 3Mtpa by 2015.
A commensurate increase in Sishen Iron Ore’s allocation on the iron ore export channel capacity from
23.5Mtpa to 35Mtpa is planned.
Extensive laboratory and pilot plant testwork was undertaken through the various phases of investigation:
- Pre-feasibility characterisation of stockpile material and mine samples;
- Feasibility characterisation of ten mine samples with confirmatory pilot plant tests; and
- Feasibility optimisation on forty-eight mine samples.
In the interest of sample representivity, significantly large primary samples of up to 3,000t were taken from
stockpiles and pit faces for pre-feasibility and feasibility investigations, with 80t primary samples being taken
for feasibility optimisation studies. These in turn were crushed before secondary samples of approximately
3t each were split out for laboratory testwork.
The testwork programme focused on selection of the best relative cut density, the generation of beneficiation
curves for various ore types and stockpiles that could be included in the geological model, prescription of the
metallurgical flowsheet and determination of design parameters for engineering design.
A Mineral Density Separator (“MDS”) which is essentially a batch jig was used for laboratory characterisation
of the various ore types and stockpiled material. MDS results were modified via a standard procedure to allow
for process imperfection. Whilst each material type has a unique beneficiation curve, the modified results
confirmed that at separation densities between 4.0g/cm3 and 4.2 g/cm3, lump and fine product at 64%Fe and
63.5%Fe, respectively, can be produced from feed between 50%Fe and 60%Fe at yields in excess of 60%.
The pilot plant tests were run in two campaigns as certain shortcomings were identified in the initial campaign.
The second campaign confirmed the MDS beneficiation algorithms for the coarse and medium jigs but not
the fine jig. Medium and fine jig capacity was also shown to be lower than originally anticipated. This was
evaluated ahead of detailed design and subsequently a fourth jigging module was included. Pyrometallurgical
testwork undertaken on the lump and fine products generally found both to compare well with current
Sishen ore.
The SEP product specifications as summarised in Table 6.3 were determined through an iterative process
between the resource beneficiation characteristics and market requirements. Laboratory and pilot test results
confirmed that these specifications will be met in practice.
| Table 6.3 SEP: Plant Product Qualities |
|
| Description |
Units |
Fe |
|
SiO2 |
|
Al2O3 |
|
K2O |
|
P |
|
Oversize |
Undersize |
|
| |
|
|
|
|
|
|
|
|
|
|
|
Max |
Max |
|
| Lump Ore |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sishen Specification |
(%) |
66.00% |
|
3.70% |
|
1.50% |
|
0.16% |
|
0.057% |
|
6.5%+25mm |
10%8mm |
|
| SEP Specification |
(%) |
64.00% |
|
5.90% |
|
1.50% |
|
0.16% |
|
0.065% |
|
6.5%+25mm |
12%8mm |
|
| Sishen Typical |
(%) |
66.27% |
|
2.93% |
|
1.25% |
|
0.15% |
|
0.055% |
|
6.4%+25mm |
6.5%8mm |
|
| SEP Expected |
(%) |
64.35% |
|
5.50% |
|
1.22% |
|
0.16% |
|
0.063% |
|
|
|
|
| Fine Ore |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sishen Specification |
(%) |
65.00% |
|
4.20% |
|
2.00% |
|
0.24% |
|
0.066% |
|
7.5%+5mm |
18%0.2mm |
|
| SEP Specification |
(%) |
63.50% |
|
6.30% |
|
2.00% |
|
0.24% |
|
0.074% |
|
10%+8mm |
18%0.2mm |
|
| Sishen Typical |
(%) |
65.52% |
|
3.26% |
|
1.59% |
|
0.19% |
|
0.066% |
|
5.1%+5mm |
8.5%0.2mm |
|
| SEP Expected |
(%) |
64.37% |
|
5.20% |
|
1.70% |
|
0.24% |
|
0.067% |
|
|
|
|
Letters of intent from existing Kumba clients support the demand for product of such chemical, physical and
pyrometallurgical quality.
The proposed SEP flowsheet and process design criteria largely recognise the testwork findings. RoM ore will
be fed to the primary gyratory crusher directly from the mine or from RoM stockpiles. Primary crusher product
drops into a rock box ahead of a scalping screen and the secondary gyratory crusher. Scalping screen
underflow and secondary crusher product drop into a rock box ahead of conveying to an intermediary
stockpile. Material withdrawn from the stockpile is conveyed overland to the closed circuit tertiary crushing
and screening plant. Screen underflow is conveyed to two pre-beneficiation blending beds. These principally
serve to blend and homogenise the feed ahead of beneficiation. They also decouple the crushing and
downstream beneficiation plant which in turn provides a maintenance buffer, improves mining equipment
utilisation and allows for continuous feed to downstream beneficiation.
Material reclaimed from the pre-beneficiation blending beds is conveyed to three identical beneficiation
modules comprising screening into a coarse (–25+8mm), a medium (–8+3mm) and a fine (–3+0.8mm)
fraction. The three fractions report separately to coarse, medium and fine jigging. Product (sinks) from the
coarse jigs is extracted via vibrating feeder ahead of screen dewatering and deposition on the lump product
bed. Product (sinks) from the medium and fine jigs is extracted via vibrating feeders ahead of two stage
screen and bunker de-watering before deposition on the fine product bed. Ore reclaimed from the product
beds is conveyed to three existing load out stations for rail despatch to clients.
Waste (floats) from all jigs is dewatered before being conveyed to the discard dump. Each module has a degrit
system comprising cyclones and dewatering screens. The –0.8+0.2mm fraction is combined with the plant
discard and the –0.2mm fraction is thickened and pumped to tailings.
Presently the design excludes the processing of the –0.8mm fraction through up current classifiers. Such
units will be tested and are likely to be included at a later stage.
Certain key aspects did require ratification before finalisation of the design. Firstly, a new generation screen
with typical design specifications to those proposed for the SEP was tested in the Sishen washing and
screening plant. The top deck did not meet efficiency claims under dry screening conditions. It is believed
however, that sufficient screening capacity has been installed in the SEP tertiary crusher plant. This has been
confirmed before finalisation of SEP screen selection. Secondly, utilisation of a bucket elevator to extract
product from below the jig is more conventional than the proposed utilisation of a screen. Screen extraction
has however, been successfully utilised in Australia at industrial scale. Screen extraction was selected on the
basis of a visit to such an installation and has been ratified during final design.
Risk mitigation activities confirmed the jig throughput capacities and indicated that an additional jig
beneficiation flow line was required to achieve the required product specifications and yields. These changes
have been incorporated into the capital and operating cost estimates of the plant.
Annual plant throughput is planned at 15.6Mtpa RoM, comprising 13.3Mtpa low grade material and 2.3Mtpa
high grade material at a planned yield of 64% to produce 10Mtpa of product (output relates to the first 10Mtpa
expansion). The plant has however, been designed to process 16.7Mtpa RoM at an average design yield of
60% to produce 10Mtpa of product.
|