Tiwest JV
The Tiwest JV mining operation has a current capacity of approximately 21Mtpa of ore. Dredging operations account for approximately 16Mtpa and the remainder (5Mtpa) is sourced via scraper operations in a dry mining operation. Combined production of the HMC of up to 800kt is transported by road to the dry separation plant at Chandala.
The mining operations at Cooljarloo are divided into two separate entities, the South Mine and the North Mine, each employing a different mining method.
South Mine: The mining operations in the South Mine consist predominantly of a dredging operation. The vegetation is first stripped within the mining limits. This stripping/clearing is undertaken in preparation for the overburden stripping by a mining contractor using track dozers. Vegetation clearing is normally 50 100m in advance of the overburden stripping operations. Once the vegetation is removed the mining contractor utilises scrapers to remove the topsoil to a nominal depth of 0.3m, normally in two cuts one of 0.05m and the second of 0.25m. Where possible this topsoil is placed directly onto land formed areas to take advantage of the active seed load.
Overburden removal is also undertaken by a mining contractor, using an excavator and haul trucks. The overburden is removed in flitches of up to 4m in depth and in minimum working widths of 50m. Mining of the overburden cycles between flitches is aimed to maintain ore exposure of at least 6 8 weeks in front of the dredges. This system also maintains a blend of overburden on the dump to maintain the dump integrity.
Overburden is hauled to the rear of the dredge pond and dumped on the beach to complete the land form. After the removal of the overburden, the ore mining is undertaken by Tiwest JV using two dredges working in a purpose built pond to pump ore directly to a floating concentrator. The smaller dredge mines to a maximum depth of 9m ahead of the larger dredge which mines to a depth of 25m. Installed dredge capacity currently exceeds the concentrator capacity. Oversize rocks and debris are removed by trommel prior to the concentrator and sand tailings are returned to the mining area for use in rehabilitation. Heavy minerals are extracted from the sands and clays and pumped from the concentrator to stockpiles.
North Mine: The North Mine is currently located approximately 5km to the north of the dredging operations in the South Mine. The mining operations are based upon a dry mining operation using track dozers to firstly remove and stockpile the vegetation. Topsoil is then removed similar the South mine operations, whilst the thin layers of overburden are removed and placed by a fleet of elevating scrapers. Ore is then removed with the same scraper fleet which deposits the ore into a hopper for feed to a trommel to remove the clay and debris. Sand is then transported to a land-based wet concentrator for separation of the heavy minerals.
As the mining progresses through the orebody, sand and clay are returned to the void and the surface reformed prior to the spreading of topsoil and eventual rehabilitation. The mining methods currently employed at each of the current operational areas are appropriate for the orebodies being exploited.
The mining contracts for overburden removal in the South Mine and for mining operations in the North Mine are currently under review and re-tender. Whilst this will not alter the current methodology in both areas it is expected that pricing will increase in line with current increases in labour and fuel costs. Productivity in these areas will however, likely increase with the change of contractor. Current equipment on the most part is aged and availability is low with the incumbent contractor reluctant to upgrade at this time of retender given the uncertainty of tenure.
|