Sishen Mine
Mining Methods: Sishen Mine is a large, mature opencast mine established in 1953 to develop the extensive local iron mineralisation and resources in the area. All the RoM ore is beneficiated and, after blending to specification on product stockpiles, is railed to Saldanha Bay for the international export sales markets or inland to the domestic customers. The Mineral Resources and Mineral Reserves have historically been derived from >60%Fe material and lower grade iron ore was stockpiled or classified as waste. An investigation into mining and processing lower grade material has been completed by Kumba and the SEP Phase I is being constructed to process >58.5%Fe material.
The regional topography is flat and access into the pit areas is provided by a number of haul roads that are generally constructed to a minimum width of 30m and at a maximum gradient of 8%. Mining operations are widespread and take place over the full area of the deposit. The pit can broadly be divided into a North, Central and South pit area. Waste dumps are located on the east and west sides of the pit, and some backfilling of mined out pit areas has already commenced in the Central and South pit area. In the longer term a greater opportunity for backfilling exists.
An in-pit crusher located in the North pit area is used to reduce haul distances and crushed ore is conveyed from the in-pit crusher to the beneficiation plant.
Mining benches are cut at 12.5m intervals although smaller equipment has been introduced to enable the mining operation to mine more selectively from the bench and flitches. The mining operation is conducted using a large fleet of conventional open pit mining equipment comprising blast hole drilling rigs, electric face shovels, and 170t and 190t off-highway trucks supported by appropriate ancillary mining equipment. Where appropriate, electric trolley assist for truck haulage is used improving the up-hill truck speeds on in-pit haul
roads and roads to the waste dumps. A small proportion of the waste rock can be free dug (16%) but the majority of the rock to be mined requires drilling and blasting. The ore material consists of haematite in enriched banded iron formation. These rocks are very hard and have a high specific gravity. The mining duty is considered to be heavy.
The mining equipment fleet is maintained on an ongoing basis, with interim major overhauls and rebuilds planned during the life of each of the primary units of mining equipment. Provision is made to replace the equipment as justified by higher maintenance costs as each unit ages. The final pit as planned will require the relocation of certain surface infrastructures due to the expansion of the open pit westwards and a 500m blasting perimeter. The likely costs for infrastructure relocations have been provided for in the capital planning and have been utilised in the open pit optimisation exercises.
Dilution, Mining Losses and Reconciliation: A mining block size of 10m x 10m x 6.25m is used for ore definition in terms of the different material categories used at the mine. These blocks can be aggregated to form a bench of 12.5m in vertical height. A block is classified according to the material type in which the centroid of the block falls. The block includes estimates for dilution and for mining loss only where the centroid of both blocks falls outside the ore zone. Sishen Mine has traditionally used six material codes to derive the Mineral Reserve estimates although product quality algorithms are used to determine the likely product. An allocation percentage is attributed to each of the material codes. The six material type codes include: four for ore to define blocks above and below a grade of 64.5%Fe as well as above and below a phosphorous content of 0.08%; one for the high density (RD>3.6) hangingwall waste; and one for the low density (RD<3.6) footwall waste. Dilution and ore loss is incorporated in the two waste material categories where the orebody outline transgresses the block boundary. From reconciliation with the actual plant feed the proportion of these material categories reporting as actual plant feed is quantified and used in defining the Mineral/Ore Reserves. The latest reconciliation indicated that the following proportions report as ore: 100% of the ore blocks with low phosphorous; 58% of the ore blocks with high phosphorous; 25% of the high density hangingwall waste and 60% of the low density footwall waste. For the latest Mineral/Ore Reserves the material codes have been expanded to some 14 categories principally to include the different combinations associated with introducing the SEP plant and to formalise the contribution from selective mining. In terms of iron ore grades the material greater than 64.5%Fe is planned to report exclusively to the Main Plant whilst material between 61%Fe and 64.5%Fe can be treated at the Main Plant or SEP Plant. Ore with a grade of some 40%Fe to 61%Fe is planned to be treated exclusively at the SEP Plant. These material codes are used in the scheduling algorithms and not all the material that is defined as ore is necessarily treated in the period of the LoM Plan. A certain amount of SEP material located towards the base of the open pit remains at the end of the LoM Plan due to the treatment capacities of the two plants. This indicates the potential for increased SEP production as envisaged by Kumba in the SEP Phase II project for later expansion.
| Table 5.1 Sishen Mine: Modifying Factors |
| Modifying Factor |
Units |
Value
|
| Ore Loss |
(%) |
n/a1 |
| Dilution |
(%) |
7.4% |
(1) |
No separate ore loss figure is available as the ore loss is captured as part of the resource definition and the material code allocation percentages are based on a five-year reconciliation. |
Mine Planning and Scheduling: Sishen Mine utilises standard industry techniques for the open pit design, scheduling and planning commencing with an open pit optimisation exercise that assists in the determination of the optimum pit for design purposes. The optimisation and design process is extensive and incorporates sufficient investigation of technical and economic parameters such as pit slope angles, existing infrastructure, boundaries, ore, stockpile and waste dumps and operating and capital costs. The reserve footprint extends for approximately 12km on strike and up to 3km on dip and ultimately the final pit is expected in parts to be 410m deep.
The open pit optimisation exercise that supports the Mineral Reserves presented in this CPR, are based on the Main Plant (=60%Fe) ore only. The SEP ore that has been included in the current Mineral Reserve statement has been derived from the material that exists below this grade but above 58.5% beneficiated Fe and is planned to be processed through the new SEP facility over the life of the Main Plant. The SEP ore was considered as waste type material for this open pit optimisation exercise. The 2006 open pit optimisation exercise will consider the SEP material as ore instead of waste. This should materially increase the size of the optimised pit, hence increase RoM reserves but also increase waste stripping costs.
The current LoM Plan reports a remaining mine life of 24 years, based on the in-situ Mineral Reserves defined and depleted with an existing SEP stockpile of some 44Mt. Sishen is thus projected to be a long life mine. The total anticipated production of ore during the LoM is some 1,200Mt of RoM ore at an overall stripping ratio of 2.8:1. A contribution of 670Mt is anticipated from Main Plant ore and 350Mt from SEP ore resulting in total headfeed of some 1,021Mt over the LoM Plan. The stockpile of 179Mt accounts for the difference between the RoM and the total plant headfeed. The annual RoM production to the Main Plant is scheduled to increase to some 33Mtpa from the current 32Mtpa from improvements to the process facility leading to product production of some 29Mtpa. The SEP ore is planned to commence production from 2007 leading to a product production of 13Mtpa in 2015. Waste stripping requirements range from some 64Mtpa to 105Mtpa over the LoM Plan. The waste stripping schedule is not undertaken according to minimum requirements and SRK consider that there exists flexibility in the planning requirements. The average stripping ratio is 2.8 : 1 and significantly less than that required (3.4 : 1) before the SEP ore was defined. However, the total material mined increases to some 183Mtpa from 2014 which is some 93Mt (100%) more than historically achieved (90Mt in 2004) and capital is included for additional mining equipment and re-builds.
|