Rosh Pinah
The Rosh Pinah tailings dam is located 1.5km South and down gradient of the plant area. Slurry residue
is currently pumped to the dam at a rate of approximately 80tph in either one of the two existing 180mm
diameter steel or HDPE pipelines. It is estimated that the in-situ density of the tailings will be in the order
of 1.5tpm3 therefore deposition on an annual basis will be approximately 660,000tpa or 440,000m3 p.a. based
on a plant efficiency of approximately 94%.
The tailings dam layout is split into three compartments, two of which are located at the top surface of the
dam at an elevation of 376.00 mamsl (24m high). The third compartment is an extensive tailings buttress
located on the southern and south western flanks of the dam at an elevation of 362.00mamsl (18m high).
All three compartments had elevated penstocks installed in 1998, before this time water was stored on top
of the dam and allowed to either evaporate or seep into the sub surface sandy gravelly soils underlying
the tailings dam. The elevated penstocks discharge into an unlined solution trench on the eastern side of the
dam. The solution trench transport the decanted supernatant water to an unlined evaporation dam located
immediately south of the tailings impoundment. There are currently no facilities in place to pump this water
back to the plant for use in the process circuit.
The machine packed division wall between the two compartments located on the top of the tailings dam has
been machine breached in several places with the objective of forming a single compartment with a total
surface area of approximately 24,3Ha. The lower compartment has a current deposition surface area in the
order of 14.2Ha. The overall area available to deposit the Rosh Pinah tailings is therefore 38,6Ha. The current
rate of rise will be in the order of 1.25mpa if the total available deposition area is utilized. It is estimated that
the closure rate of rise after five years using the entire surface area of the tailings dam to deposit tailings will
be 1.35mpa. Both rates of rise are acceptable.
It is understood that tailings disposal will be outsourced to a contractor at the end of August. Preliminary
discussions between mine management and the contractor would indicate that there is a suggestion to restrict
the deposition of tailings for the next five years onto the southern buttress dam with the objective of bringing
all compartments to the same elevation. If this option is pursued the rate of rise on the lower compartment
will increase to 3,4mpa.
|