Table 14.9 Sishen South Project: FM in ZAR Nominal Terms (2006 to 2018)
STATISTIC F. Year Units Totals 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
  Project Year   LoM 1 2 3 4 5 6 7 8 9 10 11 12 13
Production Total Headfeed (Mt) 65   1.3 3.2 2.7 2.4 3.4 3.0 3.2 3.0 2.7 2.7 3.0 3.0
Sales Volumes                                
  Main Plant                              
  – Lump (Mt) 39   0.3 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
  – Fine (Mt) 25   0.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2
  Total Sales (Mt) 65   0.6 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0
Financial – Nominal                                
  Net Revenue (ZARm) 22,579   151 688 657 727 763 804 842 884 932 970 987 1,005
  Total Working Costs (ZARm) (13,881)   (149) (394) (386) (414) (440) (454) (480) (502) (522) (553) (584) (612)
  Distribution Costs(1) (ZARm) (6,480)   (32) (177) (185) (193) (203) (213) (223) (235) (246) (259) (272) (285)
Mining and Beneficiation Costs (ZARm) (7,092)   (118) (217) (192) (210) (226) (230) (244) (254) (262) (281) (298) (312)
  Royalties (ZARm) (309)       (9) (11) (11) (12) (12) (13) (14) (14) (14) (14)
  Operating Profit (ZARm) 8,699   1 294 271 313 323 349 362 382 410 416 403 393
  Capital Expenditure (ZARm) (1,392) (491) (340) (50) (2)     (3) (46) (81) (15) (55) (84)  
Net Change in Working Capital (ZARm) (61) 40 (21) (82) (2) (7) (3) (4)   (1) (11)   2 (8)
  Tax Liability (ZARm) (2,128) 142 98 (71) (78) (91) (94) (100) (92) (87) (115) (105) (92) (114)
Final Net Free Cash  (ZARm) 5,118 (308) (262) 91 189 215 226 242 224 212 270 257 228 271
Final Net Free Cash – Real (ZARm) 2,503 (308) (250) 83 163 177 177 180 159 144 174 157 133 151

(1) Includes all costs incurred in getting the iron ore to the export terminals at the coast.